Understanding the timeline in five minutes

The timeline is the time grid that fills the right-hand part of the editor. Here's the vocabulary and the ribbon's buttons, as they really appear in the application.

The vocabulary

The "Summary" bar

Right above the grid, a collapsible line states at a glance: the number of rows, the number of blocks, the period covered and the number of working units it represents, and the number of dependencies (with any that are violated, if there are any).

The ribbon, button by button

Left to right, as observed in the application:

ButtonWhat it does
Undo / RedoUndoes or redoes the last gesture — a Ctrl+Z / Ctrl+Y shortcut also exists.
Zoom out / Zoom inChanges the display grain (day, week, month…) ; the current grain shows between the two buttons.
Today (T)Recenters the view on today's date, marked by a vertical line in the grid.
Go to a dateA date field: the view jumps straight there.
OverviewAdjusts the zoom so the whole schedule fits on screen.
Search and filter (Ctrl+F)Opens the search-and-filter panel, to keep only certain rows.
Critical pathShows or hides the critical path (the blocks whose one-day delay pushes back the schedule's end).
Mini-mapShows a reduced view of the whole schedule, with the frame of what's currently visible.
Printable preview (Ctrl+P)Opens the print / image-export preview.
VersionsOpens the schedule's version history (daily, or taken by hand).
SettingsOpens the settings modal: the time unit, active days, working hours, the reference date, the legend, printing.

What gets painted in the grid

And next

This guide gives just enough vocabulary to find your way around. To go further on a specific point, the task guides each detail one gesture: The grid and columns, The legend and the filter, A block's actions and its derived progress, etc. — see Task guides.