The calendar, closures and absences
The calendar decides which days count as working days — hence a block's real duration. This guide covers active days, closures (the whole team), and absences (one row).
Active days and working hours
In Settings › Working calendar, the WORKING DAYS section offers a checkbox per weekday (Monday to Sunday) and a Shade inactive days checkbox; WORKING HOURS sets From (hour) and To (hour) for an hourly timeline. Checking or unchecking a day immediately changes what "one working unit" means for the whole schedule. Just above, the Unit type setting (day, hour, quarter-hour…) carries its own warning: "Changing the unit type snaps blocks to the new unit's slots; Ctrl+Z restores them."
Placing a closure
Still in Settings › Working calendar, the CLOSURES AND ABSENCES section lists what already exists ("Name · start date → end date · non-working · whole schedule or one row", with a Remove button) and offers a form below it:
- Name (for example "Summer closure", "Anne's leave")
- From / To
- Kind — Non-working (the only kind observed; a colored range without being non-working is also possible depending on the setting)
- Repeat — Once, or a yearly range that replays every year
- For — The whole schedule, or restricted to a row
- Add button
A closure for the whole schedule blocks out the period for every row. A closure placed for one row (shortcut: right-click the row › Absence on this row…, which opens the same form already filled in for that row) only blocks out that row — an individual absence, not a team-wide closure.
What it changes on blocks
The form's own text states it: "A non-working range extends the blocks it crosses and pushes what follows; on rows, it only extends theirs." Verified on a minimal case: two blocks linked hard, A (Oct 5–7) immediately followed by B (Oct 8–9) — starting summary "from 2026-10-05 to 2026-10-09 — 5 working units". After placing a two-day closure (Oct 6–7) crossing A:
- A stretched out by the number of non-working days it contains — its end, on screen, moved back to the 9th (the non-working range is painted highlighted inside the block). Its duration in working units, though, didn't change.
- B, linked hard right after A, was pushed by the same number of days — its start moved back from the 8th to the 12th (the connector between the two blocks shows it).
- The summary confirms it: "from 2026-10-05 to 2026-10-13 — 5 working units" — the period stretched by four calendar days, while the working-unit count didn't move.
A block linked soft wouldn't have moved: that link type never pushes anything (see The timeline: blocks, links and milestones).
What happens when you get it wrong
- A closure with the wrong dates or on the wrong scope: Remove next to its name in the list, or Ctrl+Z right after placing it.
- An active day unchecked by mistake immediately snaps every block onto the new working slots — Ctrl+Z reverts it.
What this page doesn't cover
- The unit type, the headers shown, the reference date: neighboring settings in the same Settings › Working calendar tab, described in Understanding the timeline in five minutes.
- Coloring days (without making them non-working): a different kind of special range, not detailed here.
- The hard and soft links that decide what gets pushed: see The timeline: blocks, links and milestones.